Josh Shapiro (Gov-D Pennsylvania) signed the order. It holds state permit review until a project clears local zoning and lines up new power. In August, Michigan Senate nominee Mike Rogers (R-MI) called for a one-year freeze on new data centers. Grid operator PJM covers 13 states. Starting in mid-2027, it plans to cut off new large loads that have not lined up their own power for tight days.
Where else it's biting
- Vineland, New Jersey issued stop-work orders in August on a Microsoft-linked campus. Crews had installed equipment without local permits, and the generators had no state air permit.
- New Mexico's land commissioner rejected the pipeline for Oracle and OpenAI's Project Jupiter twice this year, pushing it to 2027.